PSAR is investing in solar. Smart for both finances and the planet.

posted Jun 12, 2017, 1:21 PM by Joyce Evans   [ updated Jun 28, 2017, 2:49 PM ]
Day 1
This week the solar company Mbar-C, who will be installing our Solar Panels and Car Port, will be busy constructing the carport portion and should be completely finished by Friday, June 16. The picture above shows the area of the parking lot where the project will take place. The following is the work schedule.
  • Monday, they will be drilling holes and lay the pilings.
  • Tuesday morning, a cement truck will fill in the holes drilled Monday, locking the pilings in place.

Day 2
  • Wednesday through Friday, Mbar-C will assemble the carport once the concrete has cured. There will be a special inspector periodically on-hand, who will be performing tests of the materials as they work.
Day 3
  • Their crew will be working, hand digging a trench through the planter and clearing a section of the planter for the boring machine to tunnel under the pavement to PSAR’s electrical room.
Day 4

Monday, June 26th

PSAR will keep you posted on the progress of the project. 

Thank you for your patience during the construction

PSAR Administrative Staff